About Lead Time

By OneGlass

Lead time is one of the most common questions we get from customers planning a glass bottle project. How long does it take from placing an order to receiving bottles in the UK? For our existing molds, the typical end-to-end lead time is around 75–90 days from deposit received to delivery in the UK. Here’s how that time breaks down, and what can affect it.

The standard 75–90 day timeline

30 days
Production
For bottles with no additional processing.
45 days
Ocean freight
Sea shipping from our factory to the UK.
10–15 days
Booking & inland transport
Space booking, port handling, and land delivery.

Production: 30 days for unprocessed bottles

For glass bottles that require no additional processing — such as colour coating, screen printing, or frosting — our production time is typically 30 days. This does depend on the number of orders already in our production plan.

Glass bottle production itself is very fast. Each of our production lines can run 6–8 different bottle types simultaneously, and each type can produce more than 10,000 bottles per day. Once we receive your deposit, we add your order to the production schedule. However, your order needs to queue behind existing scheduled runs before it can go on the machines — so the earlier you confirm, the sooner your slot is secured.

Additional processing: add around 10 days

If your bottles need post-production processing — colour coating, screen printing, frosting, or other decoration — you should allow roughly an extra 10 days. The exact additional time depends on the complexity of the processing and the finishing requirements.

New mold development: longer lead time

If your design requires a new mold, the timeline is longer. The process involves:

Because each step requires back-and-forth confirmation, new mold projects take significantly longer than orders using our existing molds. We recommend planning ahead and factoring this into your launch timeline.

Planning tip: If you’re working towards a fixed launch date, tell us your target as early as possible. For existing molds without extra processing, 75–90 days to the UK is a realistic baseline — and we’ll always confirm the current schedule and any factors that could affect your specific order.

Lead times are indicative and depend on production schedules, order volume, processing complexity, shipping conditions, and customs. Contact us for a confirmed lead time for your project.